What the provision says

13 Paragraph 3(4) (under which it is an offence for an undertaker to execute street works before the completion of certain other street works) of Schedule 3A to the 1991 Act does not apply in relation to the execution of works in the course of the authorised development.

Text as made, from legislation.gov.uk. © Crown copyright, reused under the Open Government Licence v3.0. This is the text as originally made; later amendments are not shown here.

Who it binds, and what has to be proved

Binds
a person
Conduct
breaching the provision
Fault element
Strict liability
Burden of proof
No statutory defence — prosecution proves everything

The prosecution must prove that the conduct happened. This is a strict liability offence as drafted: the provision uses no word of intention, knowledge, recklessness or negligence, so there is no need to show that a person meant to do it, knew about it, or was careless.

Intention, knowledge and carelessness are irrelevant to guilt. They may still matter a great deal to sentence.

The provision states no defence, so the prosecution bears the burden on every element of the offence.

Classifier’s reasoning: no word of intention, knowledge, recklessness or negligence in the offence or its provision.

What would breach paragraph 3(13) of SCHEDULE 14?

These are illustrations, not law. They are generated from the provision’s own words to show the shape of the offence. Whether any particular conduct is caught depends on the full text, on any amendment since, and on the facts.

  1. Doing what the provision prohibits, or failing to do what it requires under the Northampton Gateway Rail Freight Interchange Order 2019.

Penalty

Mode of trial
Not determined
Maximum fine
Not determined
Maximum prison (summary)
Not determined

no penalty is stated in this instrument; it may be in the enabling Act, or in a general penalties provision this pass did not connect to the offence.

No penalty was determined from this instrument. It may be in the enabling Act, or in a general penalties provision this pass did not connect to the offence. Absence of a figure here is not evidence that the offence carries no penalty.

Sentencing

Offences of this kind are usually sentenced under the guidelines below. This is a mapping by subject, not a finding about this provision, and the links go to a search of the Sentencing Council’s own site.

Prosecution figures

No published per-offence figure was found for this provision, and it could not be matched to a Ministry of Justice offence code. Offences created by statutory instrument very largely do not have one. Absence of a figure is not evidence that the offence is unused.

Status and lifecycle

Current status
Status not determined
Made
9 October 2019
In force from
30 October 2019
Extent
Not stated

How this was established: read from the text as made; no revised version available, so later revocation could not be ruled out.

What the instrument is for

(This note is not part of the Order) — the explanatory note published with the instrument, © Crown copyright.

This Order grants development consent for, and authorises Roxhill (Junction 15) Limited (“the undertaker”) to construct, operate and maintain the new Northampton Gateway Rail Freight Interchange together with associated development. The undertaker is authorised by the Order to acquire compulsorily land and rights over land. The Order also authorises the making of alterations to the highway network, stopping up and diversion of public rights of way and the discharge of water. A copy of the plans and book of reference referred to in this Order and certified in accordance with article 46 (certification of plans and documents) of this Order may be inspected free of charge at the offices of South Northamptonshire District Council at The Forum, Moat Lane, Towcester, NN12 6AD and at Northampton Borough Council at The Guildhall, St Giles’ Square, Northampton, NN1 1DE.

Read the full note and every offence in this instrument

How this was identified as an offence

Everything above rests on the judgement that this provision creates a criminal offence, rather than mentioning one. That judgement is made by rule, from the words of the provision, and this is the rule that made it — with a confidence of 0.90.

Basis
the provision says “it is an offence”; the provision says an offence is committed “if” something happens
Confidence
0.90 of 1.00

A provision that states a penalty for an offence created elsewhere can read very like one that creates an offence, and the rules can mistake the one for the other. If the text quoted above sets a penalty for something made an offence by another provision, treat the classification on this page with that in mind, and read the instrument.

Check the source