35 Any generator, distributor, supplier, or meter operator or any agent, contractor or sub-contractor of any…
regulation 35 of The Electricity Safety, Quality and Continuity Regulations 2002
- Status not determined
- Mixed — some elements strict, some not
- Summary only
- Energy, communications, water and utilities
This offence was read from the text as made, and no revised version was available, so a later revocation could not be ruled out. Check the current text at legislation.gov.uk.
What the provision says
35 Any generator, distributor, supplier, or meter operator or any agent, contractor or sub-contractor of any of the foregoing who fails to comply with any provision of these Regulations which applies to him, any person who fails to comply with regulation 18(3), 21,
22 or 25(1) and any consumer who fails to comply with regulation 8(4) or 34(2) shall be liable on summary conviction to
a fine not exceeding level
5 on the standard scale.
Text as made, from legislation.gov.uk. © Crown copyright, reused under the Open Government Licence v3.0. This is the text as originally made; later amendments are not shown here.
Who it binds, and what has to be proved
- Binds
- a person
- Conduct
- failing to do something the instrument requires
- Fault element
- Mixed — some elements strict, some not
- Burden of proof
- No statutory defence — prosecution proves everything
The prosecution must prove the conduct, and - for those elements the provision qualifies - the state of mind it names. The remaining elements carry no fault requirement, so they are strict.
The provision states no defence, so the prosecution bears the burden on every element of the offence.
Classifier’s reasoning: the offence itself carries no fault word, but a duty it criminalises by cross-reference uses so far as is reasonably practicable, reasonably practicable; which element that governs was not determined.
What would breach regulation 35?
These are illustrations, not law. They are generated from the provision’s own words to show the shape of the offence. Whether any particular conduct is caught depends on the full text, on any amendment since, and on the facts.
- On these words an offence is committed where a person fails to comply with regulation 18(3), 21, 22 or 25(1) and any consumer who fails to comply with regulation 8(4) or 34(2).
- Not doing what the provision requires under the Electricity Safety, Quality and Continuity Regulations 2002, by the time it requires it to be done.
- Doing it, but not in the manner or to the standard the instrument specifies.
Penalty
- Mode of trial
- Summary only — tried in a magistrates’ court
- Maximum fine
- £5,000
- Standard scale
- Level 5
- Maximum prison (summary)
- Not determined
this is the level 5 value when the instrument came into force (2003-01-31); the standard scale is keyed to the date the offence was committed, and for conduct today the same words mean an unlimited fine.
Sentencing
Offences of this kind are usually sentenced under the guidelines below. This is a mapping by subject, not a finding about this provision, and the links go to a search of the Sentencing Council’s own site.
-
Environmental offences: definitive guideline
Magistrates' courts and the Crown Court in England and Wales · in force from 1 July 2014
Covers unauthorised or harmful deposit, treatment or disposal of waste, illegal discharges to air, land and water, and the equivalent offences committed by organisations. It is the guideline that introduced turnover bands for corporate fines, so the size of the defendant company is a starting point rather than a mitigating detail.
-
Health and safety offences, corporate manslaughter and food safety and hygiene offences: definitive guideline
Magistrates' courts and the Crown Court in England and Wales · in force from 1 February 2016
Covers breaches of duty under the Health and Safety at Work etc. Act 1974 and the regulations made under it, and food safety and food hygiene offences. Sentencing turns on culpability and on the seriousness and likelihood of harm risked, not only on the harm that happened.
-
Reduction in sentence for a guilty plea: definitive guideline
All courts in England and Wales · in force from 1 June 2017
The sliding scale of credit for pleading guilty, from one third at the first stage of proceedings downwards.
-
General guideline: overarching principles
All courts in England and Wales · in force from 1 October 2019
The guideline a court uses when there is no offence-specific guideline, which is the position for the overwhelming majority of offences created by statutory instrument. It sets out how culpability and harm are assessed from first principles.
-
Totality: definitive guideline
All courts in England and Wales
How to sentence more than one offence at once so that the total is just and proportionate - frequently in point here, because regulatory prosecutions commonly charge several breaches of the same instrument.
Prosecution figures
No published per-offence figure was found for this provision, and it could not be matched to a Ministry of Justice offence code. Offences created by statutory instrument very largely do not have one. Absence of a figure is not evidence that the offence is unused.
Status and lifecycle
- Current status
- Status not determined
- Made
- 24 October 2002
- In force from
- 31 January 2003
- Extent
- Not stated
How this was established: read from the text as made; no revised version available, so later revocation could not be ruled out.
What the instrument is for
(This note is not part of the Regulations) — the explanatory note published with the instrument, © Crown copyright.
These Regulations replace the Electricity Supply Regulations 1988 (S.I. 1988/1057) and all subsequent amendments (S.I. 1990/390, S.I. 1992/2961, S.I. 1994/533, S.I. 1994/3021 and S.I. 1998/2971). These Regulations impose requirements regarding the installation and use of electrical networks and equipment owned or operated by generators, distributors (which include, in these Regulations, transmitters), and meter operators, and the participation of suppliers in providing electricity to consumers (all such persons are collectively referred to as “duty holders” in this note). Agents, contractors and sub-contractors of duty holders also have duties under these Regulations. These Regulations were notified in draft to the European Commission in accordance with Council Directive 98/34/EC (O.J. No. L 204, 21.7.1998, p. 37) as amended by Council Directive 98/48/EC (O.J. No. L 217, 5.8.1998, p. 18). A regulatory impact assessment is available and can be obtained from the Engineering Inspectorate, Department of Trade and Industry, 1 Victoria Street, London SW1H OET. The Department’s publication referred to in regulation 31(9) can be obtained from the same address. Copies of the regulatory impact assessment have been placed in the libraries of both Houses of Parliament. The British Standard Requirements referred to in regulation 1(5) is a joint publication by the British Standards Institution and The Institution of Electrical Engineers. Copies can be obtained from The Institution of Electrical Engineers, P.O. Box 96, Stevenage, United Kingdom SGI 2SD. Part I (regulations 1-5) contains introductory provisions. Regulation 1 contains defined terms; because these Regulations are targeted at technical and safety requirements, some of the defined terms have a different meaning from those used in the Electricity Act 1989 and in the Utilities Act 2000. Regulation 2 contains time limited exemptions for continued use of old equipment not complying with the requirements of the Regulations (e.g. pre-1937 cut-outs) and for the phased introduction of several new requirements (e.g. risk assessment of substations). Regulation 3 contains general duties relating to the safe use and operation of equipment, and requires risk registers to be maintained for substations and overhead lines. Regulation 4 requires duty holders to co-operate as necessary in order that they may each comply with these Regulations. Regulation 5 imposes requirements on duty holders to inspect their equipment and to maintain certain records for at least 10 years. Part II (regulations 6-10) contains provisions relating to electrical protection and earthing. Regulation 6 imposes a requirement for generators and distributors to install adequate protective devices in their networks. Regulation 7 requires generators and distributors to ensure continuity of the supply neutral conductor. Regulation 8 imposes certain requirements for connections with earth for all systems, and also for high voltage networks and for low voltage networks in particular. Regulation 9 contains requirements for distributors operating protective multiple earthing systems, including the circumstances in which earthing terminals of consumers' installations should not be connected to the distributor’s combined neutral and protective conductor. Regulation 10 contains requirements for earthing of metalwork. Part III (regulation 11) contains provisions relating to substations, specifically requirements for enclosures, safety and other signs (see Schedule 1), and fire precautions. Part IV (regulations 12-15) contains provisions relating to underground cables and associated equipment. Regulation 12 imposes restrictions on the use of underground cables. Regulation 13 imposes requirements for mechanical protection of such equipment and regulation 14 contains requirements regarding the depth and manner of installation. Regulation 15 requires generators and distributors to maintain maps of underground cables and equipment and to permit inspection by, and to provide copies to, specified persons. Part V (regulations 16-20) contains provisions relating to overhead lines. Regulation 16 specifies the equipment affected by this Part and imposes a limit on nominal voltage. Regulation 17 imposes minimum heights for overhead electric lines and other cables (with further requirements in Schedule 2). Regulation 18 contains requirements relating to insulation and protection of such lines. Regulation 19 imposes requirements to prevent access to high voltage overhead conductors and to fix safety signs to supports for overhead lines (see Schedule 1). Regulation 20 relates to stay wires for supports carrying overhead lines. Part VI (regulations 21 and 22) contains provisions relating to generation. Regulation 21 requires persons to ensure switched alternative sources of energy remain isolated from a distributor’s network. Regulation 22 imposes requirements on persons intending to operate a source of energy in parallel with a distributor’s network. Part VII (regulations 23-29) contains general requirements relating to the provision of electricity to consumers' installations and other networks. Regulation 23 requires distributors to take precautions against supply failure. Regulation 24 contains provisions relating to distributors' and meter operators' equipment on consumers' premises, including electrical protection, security and connections to consumers' earthing terminals. Regulation 25 specifies requirements for persons connecting new installations or new networks to a distributor’s network, with provision for settling disputes arising from a distributor’s delay in giving or refusal to give consent for connections. Regulation 26 specifies the procedure if a distributor considers that an installation is unsafe or is causing interference and the procedure to challenge the distributor’s refusal to give or continue a supply. Regulation 27 imposes requirements to give information relating to a supply and to maintain the quality of supply within certain tolerance limits. Regulation 28 requires other information affecting a consumer to be provided on request. Regulation 29 permits distributors to discontinue a supply for such period as may be necessary under certain circumstances. Part VIII (regulations 30-36) contains miscellaneous provisions. Regulation 30 entitles inspectors appointed by the Secretary of State to the provision of facilities and information where an inspection of a generator’s or distributor’s network or equipment is being carried out. Regulation 31 and Schedule 3 contain a requirement on generators, distributors and meter operators to give particulars to the Secretary of State relating to accidents and other events involving their networks and equipment and domestic consumers' installations. Regulation 32 and Schedule 4 contain a requirement on a distributor to give notice to the Secretary of State of specified interruptions of supply to consumers. Regulation 33 permits the Secretary of State to grant exemptions from the Regulations, and regulation 34 enables the Secretary of State to prohibit the use of networks or equipment owned or operated by duty holders or of a consumer’s installation in specified circumstances, with provision for settling disputes. Regulation 35 provides that specified persons who fail to comply with specified provisions of the Regulations commit an offence under section 29 of the Electricity Act 1989. Regulation 36 and Schedule 5 specify Regulations (the Electricity Supply Regulations 1988 and subsequent amendments) which are revoked by these Regulations.
Read the full note and every offence in this instrument
What Parliament said
Mentions of this instrument in Hansard. Parliamentary material is reused under the Open Parliament Licence v3.0.
-
Power Failures (London And Birmingham)
Commons · 22 January 2004 · The Minister for Energy, E-Commerce and Postal Services (Mr. Stephen Timms)
On 10 September I announced that DTI's engineering inspectorate would be launching an investigation into the power cuts that affected large areas of south London and parts of Kent on 28 August, and the West Midlands on 5 September. In particular, investigators were to check for compliance with the Electricity Safety, Quality and Continuity Regulations 2002. With the agreement of the Secretary of State for…
-
Power Cuts (North-West Kent)
Commons · 20 October 2009 · The Parliamentary Under-Secretary of State for Energy and Climate Change (Mr. David Kidney)
I congratulate the hon. Member for Bexleyheath and Crayford (Mr. Evennett) on securing this debate on an incident that clearly caused much disruption to those who lost their electricity supply for a long period. This is a prime example of what an Adjournment debate is for—Members speaking up passionately on behalf of people in their area who have had a hard time, and in this case, seem to have been treated badly in…
-
Planning and Infrastructure Bill
Commons · 9 June 2025 · Madam Deputy Speaker (Ms Nusrat Ghani)
With this it will be convenient to discuss the following: New clause 1— Steps to be taken when exercising functions under Part 3— “When exercising any function or fulfilling any duty under Part 3 of this Act, the Secretary of State and Natural England must take all reasonable steps to— (a) avoid, prevent and reduce any identified significant adverse effects on the environment, and only permit such adverse effects…
-
Planning and Infrastructure Bill
Lords · 1 September 2025 · Lord Khan of Burnley (Lab)
My Lords, let me take this opportunity to welcome the noble Baroness, Lady Bloomfield, to her place on the Front Bench. I look forward to the exchanges ahead. I turn to Amendments 78 and 79A, tabled by the noble Earl, Lord Russell, the noble Lord, Lord Swire, and the noble Baroness, Lady Coffey. I thank them both for tabling these amendments and for their interest in and commitment to improving grid capacity and…
How this was identified as an offence
Everything above rests on the judgement that this provision creates a criminal offence, rather than mentioning one. That judgement is made by rule, from the words of the provision, and this is the rule that made it — with a confidence of 0.72.
- Basis
- the provision states liability on summary conviction; the provision states a penalty in older drafting
- Confidence
- 0.72 of 1.00
A provision that states a penalty for an offence created elsewhere can read very like one that creates an offence, and the rules can mistake the one for the other. If the text quoted above sets a penalty for something made an offence by another provision, treat the classification on this page with that in mind, and read the instrument.
Check the source
- This provision on legislation.gov.uk The authoritative text. Check it before relying on anything here.
- The Electricity Safety, Quality and Continuity Regulations 2002 Every offence this instrument creates, and its explanatory note
- Energy, communications, water and utilitiesOther offences on the same subject
- Offences created in 2002